What is the duration of the project? How much slack is currently available in the non-critical path?

What is the duration of the project? How much slack is currently available in the non-critical path?

In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.

Activity Task Predecessors Duration Activity Cost
A Sign Contract None 5 days $5,000
B Design Survey A 3 days $1,500
C Identify Audience A 7 days $1,000
D Run Survey B, C 30 days $6,000
E Analyze Results D 5 days $3,000
F Create Presentation E 5 days $1,000
G Present to Client E, F 2 days $3,000
Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module’s lecture.
What is the duration of the project?
How much slack is currently available in the non-critical path?
How long are the project and feeder buffers?


The post What is the duration of the project? How much slack is currently available in the non-critical path? appeared first on Ink Essays.

What is the duration of the project? How much slack is currently available in the non-critical path?



Logo
.
CLICK HERE TO ORDER 100% ORIGINAL PAPERS AT PrimeWritersBay.com

Comments

Popular posts from this blog

An Inventory

Develop 5 key success factors for their industry, whether it be RSO, non-profit, etc

identify some of the key elements to a successful audit.